  • Samra v Sandwell MBC (2026) UKUT 83 (LC): A Demolished Party Wall, a 3-4 Metre Excavation and £547,039 Compensation, a £30,000 Party Wall Costs Deduction Rejected, Lessons for Building Owners and Expert Surveyors (November 2026)

    On 27 February 2026 the Upper Tribunal (Lands Chamber) determined compensation at £547,039 for a half-built housing site in Smethwick. The site had been compulsorily acquired after damage to the houses on either side and the collapse of a deep trench [1]. Most of the argument was between two expert valuers. They agreed what a clean site was worth. They disagreed on how much a buyer would deduct for a missing party wall, failed underpinning and negotiations with the neighbours.

    Key Takeaways

    • The valuers agreed a base value of £400,000 for the cleared site, ignoring the damage next door. The dispute was about adjustments to that figure.
    • The council’s valuer deducted £239,000. The claimants’ valuer deducted £50,000. The Tribunal allowed £18,000 towards rebuilding the party wall and £54,000 for other items.
    • A £30,000 deduction for negotiation and legal costs, including Party Wall Act notices and agreements, was rejected in full.
    • This is a first-instance valuation decision, not a ruling on the Party Wall etc. Act 1996.

    What happened to the party wall on site?

    The site was 103 Barclay Road and the open land beside it. Number 103 had shared a party wall with number 101, a house built in 1905. Number 109 stood on the other side [1].

    All three buildings had structural problems. A 2009 report found the buttresses propping 103 were built on loose fill. Trial pits at 101 found unstable front foundations. At 109, the gable wall sat on a brick corbel footing with no real foundation.

    The owners, a father and son, obtained planning permission on 15 June 2011 for three houses with basements. Number 103 was substantially demolished by early 2011. The rear of the site was then dug out to a depth of 3-4 metres over about 300 square metres.

    The gable of 109 was underpinned, but the front corner subsided and the brickwork cracked. In February 2014 the owner of 101 told the council of concerns about the party wall. An inspection found excessive movement needing immediate attention. On 17 February 2014 a worker was trapped to the waist when a newly dug trench collapsed. The Health and Safety Executive became involved and work stopped. By the valuation date of 7 May 2014 the party wall had been removed and the exposed side of 101 was covered with a membrane.

    What does the decision say about Party Wall Act procedure?

    Very little. The decision does not say whether notices were served under the Party Wall etc. Act 1996 before the demolition, excavation or underpinning. It records no party wall award and no appointed party wall surveyors. The Tribunal was valuing land, not deciding liability to the neighbours.

    Party wall matters appear as fact, as cost and as risk. The wall moved and was taken down. In September 2014 a building surveyor acting for the owner of 101 set out four reinstatement options, priced from £87,000 to £102,000 plus VAT where costed. The council chose Option 3A, a new gable wall with a strip of land 1.2 metres wide passing to 101. The valuers then had to judge what a buyer would allow for dealing with the neighbours.

    How did the two valuers differ?

    The claimants called a valuer and a building surveyor. The council called a valuer from District Valuer Services.

    Item Claimants’ valuer Council’s valuer Tribunal
    Buyer’s half share of remedial works to 101 and 109 £25,000 £48,000 £18,000 (101 only)
    Negotiation and legal costs, including Party Wall Act notices Within a £25,000 general allowance £30,000 Nil
    Disturbance costs at 101 and 109 Within general allowance £30,000 £5,000
    Extra contingency and extra profit Within general allowance £23,000 and £60,000 £23,000 and £24,000
    Value added by works already done £156,750 Nil £121,000

    The Tribunal also allowed £2,000 for shared sewer repairs. It allowed nothing for the council valuer’s other items: garden wall stabilisation, a sterilised strip beside 109, a fresh planning application, and extra finance and holding costs.

    Why did the Tribunal prefer the lower party wall figure?

    The council’s valuer placed most weight on the like-for-like estimate of £102,000 plus VAT. That came from surveyors instructed by the owner of 101, and the Tribunal said it would need a very compelling reason to follow it. None was shown.

    The only costing for rebuilding the wall as part of the whole scheme came from the claimants’ building surveyor, at £48,700 plus VAT. No other expert challenged it. The Tribunal stripped out demolition and propping already done, adjusted for one saving, and reached £36,000. Both valuers assumed the buyer and the owner of 101 would split the cost equally, so the deduction was £18,000 [1]. For 109, it found no basis for any allowance.

    The Tribunal also added £121,000 for work already done: slab removal, excavation, retaining boundary walls and half the cost of the outbuildings.

    Why was the £30,000 for party wall negotiations refused?

    The council’s valuer allowed £15,000 for each neighbour to cover negotiations, Party Wall Act notices and agreements, and changes to title.

    The Tribunal disagreed. An experienced developer would identify these hurdles before bidding, and a contingency would already be in the base value. Adding more on spot figures was “at best opportunistic, and at the worse double counting” [1].

    On disturbance costs, where the valuers had simply used judgement, it observed “there was no science involved” and allowed £5,000, noting both neighbours were insured.

    The expert evidence lessons

    Experts in the Lands Chamber, like those under CPR Part 35 in the courts, owe their duty to the tribunal and must give reasoned opinions. Four points stand out.

    • Show the workings. The Tribunal wanted to see the detailed valuation behind the agreed base value. None was produced.
    • Avoid a “pick and mix” approach. The Tribunal used that phrase for a list of separate risk deductions that overlapped.
    • Check where a figure came from. An estimate prepared for a neighbour is not neutral evidence of cost.
    • Use the right discipline. Unchallenged building surveyor costings beat a valuer’s range of estimates.

    Practical lessons for London owners and surveyors

    This case happened in the West Midlands, not London. The ingredients are familiar in London all the same: old terraces on shallow footings and new basement schemes.

    For building owners and developers, the facts show how quickly deep excavation beside a weak neighbouring building can stop a project. Early structural advice and early contact with adjoining owners matter.

    For adjoining owners, the events at 101 are a reminder to report movement promptly and take surveying advice on reinstatement.

    Surveyors acting as experts should cost party wall risk from evidence and explain why it is not already in the land value.

    Frequently Asked Questions

    Did the Tribunal decide that the Party Wall etc. Act 1996 was breached?

    No. The decision does not address whether notices were served or awards made. It deals with compensation for compulsory purchase.

    Who paid for rebuilding the wall at 101?

    The decision records that the owner of 101 had insurance cover on a like-for-like basis and that the council carried out Option 3A. For valuation purposes, both valuers assumed an equal split between a buyer and the owner of 101.

    Is the decision binding in other cases?

    It is a first-instance valuation that turns on its own facts and evidence. It sets no general rule on party wall law. Any appeal to the Court of Appeal is on a point of law, with permission.

    Conclusion

    Samra shows how party wall problems become numbers in a valuation. The Tribunal accepted costed items and refused round sums that repeated risk already priced in. Owners planning excavation near a shared or neighbouring wall should take party wall and structural advice before work starts. This article is general information, not legal advice.

    References

    1. Samra v Sandwell Metropolitan Borough Council (2026) UKUT 83 (LC), Upper Tribunal (Lands Chamber), 27 February 2026. caselaw.nationalarchives.gov.uk.