Looking for expert solutions?
Request a Quote

Tag: extension of time

  • Clerkenwell Lifestyle v HG Construction (2026) EWHC 1406 (TCC): Party Wall Delays, a £57,145 Fee Split and Why an Employer’s Agent’s Emails Did Not Rewrite the Completion Dates, Lessons for London Party Wall Disputes (November 2026)

    A scaffold stayed up too long over a London laneway, the party wall award needed an addendum, and the extra party wall fees came to £57,145. An email proposed that employer and contractor split them. Three years later that same email exchange was at the centre of a High Court fight over nearly £1m in liquidated damages. The contractor lost. The case shows how party wall award delays can ripple through a whole project when the paperwork is informal [1].

    Key Takeaways

    • The court enforced an adjudicator’s decision for £955,943.43 plus his fees.
    • Emails about party wall matters and extensions of time were not a binding agreement to revise the completion dates.
    • The court did not decide any question under the Party Wall etc. Act 1996. Party wall issues were part of the background that drove the delay negotiations.
    • An employer’s agent’s authority comes from the contract. It did not stretch to making new contractual deals.

    What Happened

    Clerkenwell Lifestyle (UK) Limited was the employer on a London development with residential, hotel and office elements. HG Construction Limited was the contractor. The employer’s agent was a firm of surveyors.

    In December 2022 the contractor asked for a 12-week extension of time. On 1 February 2023 the employer’s agent emailed proposals dealing with what he called the ongoing party wall matters and the contractor’s two extension of time requests. Some of the proposals concerned the party wall addendum award.

    On 8 February 2023, after a conversation about a target date for completing the addendum award, he sent final proposals. The contractor replied the same day confirming agreement.

    Proposal in the 8 February 2023 email Detail
    Additional party wall fees from delay in removing scaffold £57,145 already paid by the client, to be split £28,572.50 each
    Cost of reinstating the scaffold About £40,000, client to share up to £20,000
    Hotel contract 12 weeks, revised completion 12 September 2023
    Office contract 10 weeks
    Delay from the scaffold and party wall addendum Not included, to be dealt with separately

    The works finished much later. The employer withheld £500,230 in liquidated damages between July 2024 and February 2025, and a further £1,161,770 was claimed in November 2024.

    The Adjudication and the Court Case

    The dispute went to adjudication. The adjudicator considered expert delay evidence and fixed revised completion dates of 12 November 2023 for the residential section and 21 October 2023 for the hotel section. His decision was dated 5 January 2026.

    The employer applied to enforce it. The contractor responded with its own claim. It said the February 2023 emails were a binding agreement on new completion dates, which the adjudicator had failed to apply.

    Mrs Justice Jefford gave judgment on 12 June 2026 [1]. She held that:

    1. There was nothing in the contractor’s arguments on jurisdiction or natural justice.
    2. No binding agreement was made on 8 February 2023. Read properly, the emails were not offers to enter a contract revising the completion dates.
    3. Summary judgment would be granted for £955,943.43, together with the adjudicator’s fees.

    She added, briefly, that the contract defined the employer’s agent’s authority. It allowed him to issue and receive notices, instructions and the like. It did not extend to entering further contractual agreements for the employer.

    Where the Party Wall Award Came In

    Under the Party Wall etc. Act 1996, a building owner who plans notifiable work serves notice on adjoining owners. If there is a dispute, surveyors are appointed and settle it by an award. When the works change, or access arrangements such as scaffolding over a neighbour’s land run on, an addendum award is often needed.

    That takes time and costs money. The building owner usually pays the surveyors’ reasonable fees in the first instance. In this case the extra fees were linked to delay in taking down a scaffold. The parties tried to share that cost by email, alongside a wider deal on time.

    The party wall process ran on its own track. The building contract did not say clearly who carried the risk when the two tracks collided.

    Lessons for London Building Owners and Contractors

    • Programme the party wall process early. Notices, awards and any addendum award should sit on the critical path, not beside it.
    • Allocate the risk in the contract. Say who bears delay and extra surveyors’ fees if an award is late or scaffolding overruns.
    • Do not rely on informal emails. If completion dates are being changed, use the contract’s formal machinery or a signed variation.
    • Check authority. A surveyor or agent administering the contract may not be able to bind the employer to a new bargain.
    • Expect adjudicators’ decisions to be enforced. The court will rarely look behind them.

    Lessons for Party Wall Surveyors

    • Record clearly why additional fees have arisen, and for whose default.
    • Give realistic target dates for an addendum award, and keep both owners’ teams informed.
    • Keep party wall correspondence separate from contractual negotiations between employer and contractor.
    • Where delay is disputed later, contemporaneous records will be used by the delay experts.

    Frequently Asked Questions

    Did the court rule on the Party Wall Act?
    No. It ruled on contract formation and adjudication enforcement. Party wall matters were background.

    What is an addendum party wall award?
    A further award that deals with changes or matters not covered by the original award.

    Who pays party wall surveyors’ fees?
    Usually the building owner, although an award can provide otherwise where costs are caused by a party’s conduct.

    Was the £57,145 fee split enforced?
    The court was not asked to enforce the split. It decided only that the emails did not fix new completion dates.

    Conclusion

    Party wall award delays are a common source of friction between developers and contractors in London. This case shows the cost of leaving the consequences to email. Building owners should bring a party wall surveyor in at design stage and make sure the building contract deals expressly with party wall risk. This article is general information only and is not legal advice.

    References

    1. Tcc. caselaw.nationalarchives.gov.uk.